We refurbished this guest bedroom starting by putting in new LVP flooring and baseboards, we put in a new alder window sill, bifold closet doors and repainted the trim.
The deck is finished and is just waiting on staining, the front step is getting finished up, and the doorknobs and pulls for the kitchen have been installed and the kitchen is prepped for putting the
We continued to wrap up the deck under structure, the flooring inside has started installation and while we were replacing the siding we noticed that a water line had frozen then broke once it warmed
Prep for the kitchen and bathroom renovations is underway, we are finishing up with the places that needed insulation to be redone and putting sheetrock over it. The pumphouse is all painted and the s