We were hired to fix up the clients green house and put on a new polycarbonate roof panel. Their rafters were falling apart so we replaced them when we replaced the roof.
We continued to wrap up the deck under structure, the flooring inside has started installation and while we were replacing the siding we noticed that a water line had frozen then broke once it warmed
Prep for the kitchen and bathroom renovations is underway, we are finishing up with the places that needed insulation to be redone and putting sheetrock over it. The pumphouse is all painted and the s
Electrical and water lines were put in, and are about to be covered and graded over. The garage skirt has been finished, all of the trims and window sills have been created which will be put in soon.